Industry

The addition included a shipping and receiving office, mechanical room, electrical room, new staff toilets with locker rooms and shower facilities, new break rooms (smoking and non-smoking) and a dust collection room, in a 76,460 square foot footprint. A 5,600 square foot mechanical mezzanine was provided above the break room/toilet room area and a 1,800 square foot mechanical mezzanine was provided above the mechanical room.

A pre-fabricated clean room was installed in the addition to replace the existing clean room that was demolished. The existing entrance lobby was demolished and replaced with a larger updated lobby with conference rooms and toilet facility. The existing office and break room areas were renovated to provide additional office space and conference rooms. The existing building remained operational throughout the construction process.

The entire project was completed (including design and construction) in 14 months.